2020 89001 overhaul completed
89001 moved to Toton for painting
89001 returns to Barrow Hill after repainting
89001 moved to Soho depot for live testing
2021 89001 completes live testing then low-speed movement testing at Soho depot
89001 returns to Barrow Hill
2022 Design work and parts procurement carried out for 89001's main line equipment
89001 moves to Loughborough for main line equipment installation and other works
2023 89001 main line equipment installation continues at Loughborough
2024 89001 main line equipment installation continues at Loughborough
89001 system testing carried out at Loughborough, including live 25 kV testing
89001 hauled to Crewe for further testing
2025 89001 testing continued and other 'behind the scenes' activities completed.
89001 works under its own power on the main line for the first time in 25 years on the nights of 29 - 30 September and 30 September - 1 October 2025.